Issues and Options Document

Search representations

Results for Essex County Council search

New search New search

Comment

Issues and Options Document

Wallasea Island and the RSPB's Wild Coast Project

Representation ID: 37076

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

SP5.3 Wallasea Island and the RSPB Wild Coast Project

Paragraph 10.34 Options identified for Wallasea Island and the RSPB's Wild Coast Project:
A. Retain the current policy which supports the Wallasea Island Wild Coast Project
B. Continue to support further development at Essex Marina as per current policy
C. Do not support further development at Essex Marina

ECC Comments

ECC would expect RDC to develop a policy approach for based on evidence and in accordance with the NPPF.

In respect of Option A, ECC would anticipate the strategy for Wallasea Island and the RSPB's Wild Coast project, to be developed with a combination of the options, based on evidence and in accordance with the NPPF including consideration for a project level HRA and appropriate mitigation for recreational disturbance.
ECC would recommend the need for a holistic approach within the context of the wider emerging spatial strategy, as well as the other emerging strategies in respect of open space, green space, nature conservation, rural diversification, tourism green infrastructure and sustainable travel. A balanced approach is considered necessary to both support the Wallasea project and improvements to accessibility, whilst ensure this would be sustainable with minimal ecological impact to ensure its survival and viability as a visitor destination.

In respect of Options B & C in relation to the Essex Marina, ECC would expect a policy approach to be developed based on evidence and in accordance with the NPPF.

Comment

Issues and Options Document

Landscape Character

Representation ID: 37077

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

SP5.4 Landscape Character;

Paragraph 10.35 ECC notes and welcomes inclusion of this section and the importance and use of Landscape Character Assessments as part of the baseline criteria for any development proposal. The principle of this approach is supported and should ensure the existing landscape elements are retained and that any new elements should enhance the overall landscape character.

Paragraph 10.44 Options identified for Landscape Character:
A. Retain the current policies on the Upper Roach Valley
B. Retain the current policies on the Coastal Protection Belt
C. Develop a broad policy on landscape character
D. Ensure consistency throughout Development Management Plan policies in relation to supporting development in appropriate landscape character areas and special landscapes.
E. Do not have a policy on landscape character

ECC Comments

ECC would anticipate a combination of the options A-D to be developed based upon evidence and in accordance with NPPF.

ECC does not support Option E for the reasons stated within the "justification", it is considered contrary to NPPF (paragraph156).

Comment

Issues and Options Document

Protecting and Enhancing Heritage and Culture

Representation ID: 37078

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

SP5.5 Protecting and Enhancing Heritage and Culture

Paragraph 10.45 ECC notes and welcomes the reference to the EDG, within this section and throughout the Issues and Options Report; however as this EDG is being revised and now includes sections such as Green infrastructure, Garden Communities and SUDS, which could form other key adoptable guidelines for future development.

ECC recommend that the new revised EDG is taken into account in the ongoing preparation of the draft Local Plan and ECC would welcome the opportunity to work with RDC on this matter.

Comment

Issues and Options Document

Good Design and Building Efficiency

Representation ID: 37079

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

SP5.6 Good Design and Building Efficiency

Paragraph 10.54 ECC recommend that this section is updated to reflect the updates and changes within the revised EDG 2018, which now specifically addresses health and wellbeing requirements. ECC can confirm that Sports England has been engaged with the revisions to the EDG, to include the Sport England - Active Design Principles 2015; which is supported by Public Health England and is consistent with the overall approach to health and wellbeing.

Paragraph 10.57 ECC recommend that a reference should be included to require the sustainable use of minerals in the construction of approved developments. This would be consistent with Strategic Objective 12 which aims to make best use of mineral resources, in accordance with the NPPF.

Paragraph 10.62 Options identified in relation to ensuring design principles are appropriate:
A. Retain the existing policies on design.
Ensure design policies make specific reference to Secured by Design, and the need to strike an appropriate balance between urban design and security.
C. Retain current guidance within our Supplementary Planning Documents.
D. Develop specific design principles for individual towns and villages building on the current guidance within our Supplementary Planning Documents.

ECC Comments

ECC would anticipate a combination of the options A-D to be developed based upon evidence and in accordance with NPPF.

ECC recommends the following Guidance and Evidence is also taken into account to inform the emerging Local Plan:
* The Revised EDG (to be published in February 2018)
* Sport England - Active Design Principles 2015 (which provide updates which specifically include health and well-being requirements and the creation of inclusive and active places. ECC can confirm that Sports England has been engaged with the revisions to the EDG, to include the; which is supported by Public Health England and is consistent with the overall approach to health and wellbeing.

In respect of Option A, ECC considered this option would need to be amended to take into account changes in national policy and guidance, including the removal of the Code for Sustainable Homes.

In respect of Option B, ECC consider the guidance within the Revised EDG to be applicable and relevant.

Paragraph 10.63 Options for building efficiency standards for new homes, and new commercial and industrial buildings.
E. Remove reference to the Code for Sustainable Homes and replace with a simpler policy on water efficiency.
F. Continue to drive up energy efficiency standards for new homes through replacing the Code for Sustainable Homes with one that focuses on energy, thermal and water efficiency in particular.
G. Do not have a policy on energy efficiency standards for new homes.
H. Retain existing policy on BREEAM.
I. Amend the existing policy on BREEAM to apply to only certain types of buildings.
J. Include a specific policy on the efficiency of conversions, extensions and alterations to existing homes.
K. Do not have a policy on energy efficiency standards for conversions, extensions and alterations to existing homes.

ECC Comments

ECC would anticipate a combination of the options E-F and H-J to be developed based upon evidence and in accordance with NPPF (paragraph 156).

In respect of Option E, whilst the removal of reference to the "Code for Sustainable Homes" would be appropriate, there would be a need to ensure an appropriate approach to water efficiency is developed, in accordance with the NPPF to address the broad principles being developed within the emerging vision, strategic objectives and spatial strategy (as outlined in Option C) and to incorporate the standard for energy efficiency within Option F to promote sustainable development, and resilience to climate change, in accordance with the NPPF.

In respect of Option J, this is supported by ECC and is considered to be consistent with best practice, for example the approach contained in Uttlesford District Council's Supplementary Planning Document on home extensions to reduce carbon dioxide emissions from existing building.

ECC does not support Options G & K, for the reasons stated within the respective justifications, they are it is considered contrary to the NPPF (paragraph 156) and the emerging vision and strategic objectives of the draft Local Plan.

Comment

Issues and Options Document

Air Quality

Representation ID: 37080

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

SP5.7 Air Quality

Paragraph 10.64 ECC recommends that the scope and content of this section is expanded to include the latest national policy advice including the "National Air Quality Plan (2017)" published by DEFRA in July 2017, and the designation of the A127 to the east of Rayleigh Weir as an area having possible air quality issues.
Paragraph 10.69 ECC recommends inclusion and reference to the adoption of the AQMP for Rayleigh should be updated to say it was adopted in 2017 as this document has been issued after the date of adoption

Paragraph 10.72. Options in relation to Air Quality:

A. Retain the existing policies on air quality
B. Continue to promote clean air initiatives, such as sustainable ways to travel and renewable energy projects
C. Support, where appropriate, the actions put forward in the Rayleigh Town Centre Air Quality Action Plan
D. Do not have a policy on air quality
ECC Comments
ECC would anticipate a RDC to develop a combination of options, based on evidence and in accordance with the NPPF and DEFRA's National Air Quality Plan (2017), which specifically designates the A127 to the east of Rayleigh Weir as having possible air quality issues.

ECC recommends that consideration is also given to the use and role of wider sustainable development principles including green infrastructure, green spaces and green design principles to provide an opportunity to enhance the environment and support wider health.

ECC does not support Option D, for the reasons stated in the justification, it is considered contrary to NPPF (Paragraph 156), the National Air Quality Plan (Defra 2017) legislation, and the emerging vision and strategic objectives of the draft local plan.

Comment

Issues and Options Document

Mix of Affordable Homes

Representation ID: 37081

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

DETAILED POLICY CONSIDERATIONS (SECTION 11)

ECC notes the majority of the issues identified within this section concern detailed matters, below the overarching strategic polices and principles addressed in the preceding sections of the ECC response to the Issues and Options consultation.
The principle of the approach is noted, however, ECC would anticipate all the themes and options to be developed, based on evidence and in accordance with the NPPF, taking into account the outcomes of the wider emerging spatial strategies and principles being developed within this Issues and Options consultation, as part of the preparation of the Local Plan.

In addition to the above, ECC can provide the following detailed comments on specific themes:

D.P1.1 Mix of Affordable Housing

Paragraph 11.5 Options to address the split between affordable housing products:
F. Retain the current affordable homes split (80% social and 20% intermediate) where a scheme meets the prescribed threshold
G. Amend the split taking into account any changes in national planning policy and guidance (if the definition of affordable homes is widened to include other products)
H. Do not have a prescribed split in a policy

ECC Comments

ECC would anticipate a RDC to develop a combination of options, based on evidence and in accordance with the NPPF

Please refer to ECC's comments in response to SP1.1 (see Paragraphs 6.30, 6.31 and 6.32) above which equally apply to this option; and in particular ECC's recommendations for consideration to be given to the provision of key worker homes through the affordable housing schemes, to support the needs of healthcare providers (see paragraph 6.31)

Comment

Issues and Options Document

Development of Previously Developed Land in the Green Belt

Representation ID: 37082

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

DP1.8 Options for development of Brownfield (Previously Developed) Land in the Green Belt in the future
A. Retain the current policy on previously developed land
B. Do not have a policy on previously developed land

ECC Comments

ECC would anticipate the approach to the development of Brownfield Land in the Green Belt, to be developed based on evidence and in accordance with the NPPF, as stated in ECC's response to SP5.1 and paragraph 10.16 regarding the policy approach to Green Belt, the need for a Review of the Green Belt Boundary.

ECC does not support Option B for the reasons stated within the justification, and it is considered contrary to the NPPF (paragraphs 79-92).

Comment

Issues and Options Document

Parking Standards and Traffic Management

Representation ID: 37083

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

DP1.10 Parking standards and Traffic Management

Paragraph 11.57 Options identified for Parking and Traffic Management:
A. Retain our broad policy on parking standards and remove our Development Management Plan
B. Retain our current approach to traffic management
C. Do not have policies on parking and traffic management.

ECC Comments

ECC would expect RDC to develop a combination of options A and B, based on evidence and in accordance with the NPPF.

Please also refer to ECC's response to highway infrastructure (Section 8) regarding the Local and Strategic Highway Network and Sustainable Travel. There is a need for greater emphasis to be placed on an integrated package of transport solutions, which is applicable to Parking Standards and Traffic Management. Please also refer to ECC's earlier comments in Sections 6-8, regarding the development of sustainable communities, and in particular active design principles, promotion of healthy communities and the revised EDG to be applicable. This is necessary to ensure a holistic approach and consistency across the emerging vision and strategic objectives within the draft Local Plan.

In respect of Option B, this is partially supported by ECC, given the need to ensure that the policy is strengthened to provide an appropriate level of off street parking and to fully mitigate the impact of development (as set out in the traffic management plan), however there may be the potential to combine these options into one policy.

ECC would welcome the opportunity to explore this further with RDC as part of the preparation of the Local Plan.

ECC does not support Option C, for the reasons stated in the justification; it is considered contrary to NPPF (paragraph 156 & 157), the Essex LTP, EPOA's Parking Standards Design and Good Practice Guide; and the revised EDG.

Comment

Issues and Options Document

Homes Businesses

Representation ID: 37084

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

D.P1.11 Home Businesses

Paragraph 11.61 Options to deal with home businesses:
A. Retain the current policy
B. Take a more restrictive approach to home businesses
C. Take a more flexible approach to home Businesses
D. Do not have a policy on home businesses

ECC Comments

ECC would expect RDC to develop a combination of the options A-C, based on evidence and in accordance with the NPPF.

In respect of Option C, ECC would support a more flexible approach to home businesses, taking into account the balances within this section and the inter-relationship and links to ECC's earlier comments regarding the ambition for communication infrastructure (improvements to broadband coverage and speed) as well as the need for "grow on space", to accommodate businesses as they become more successful and need more space from which to operate.

Further details on this are set out in ECC's response to meeting business needs (SP1.7 and paragraph 6.87); the options to support employment and economic growth (paragraphs 6.94 & 6.96); and Communication Infrastructure and the options to improve broadband coverage and speed including ultrafast broadband (SP3.3 and paragraphs 8.43 & 8.44).

ECC's considers there to be a need for a holistic approach and consistency across the emerging vision and strategic objectives within the draft Local Plan.

ECC does not support Option C for the reasons stated within the justification, it is considered contrary to the emerging vision and strategic objectives within the draft Local Plan.

Comment

Issues and Options Document

How have you assessed the sustainability impacts?

Representation ID: 37085

Received: 06/03/2018

Respondent: Essex County Council

Representation Summary:

DRAFT SUSTAINABILITY APPRAISAL

ECC consider the SA to be a good example of an initial Regulation 18 'Issues and Options' appraisal, exploring the sustainability considerations of a wide range of strategic options and assessing them to the same level of detail.
Whilst not a criticism of the SA, it is considered that the options explored surrounding OAN possibilities within the Plan could be expanded upon within the SA. The Plan, at Table 2 (South Essex Housing Market Area - OAN for new homes (Source: South Essex SHMA Addendum 2017)) indicates a range of between 331 and 361 homes per year. Although the upper and lower figures displayed are perhaps not distinctively different to warrant separate assessment within the SA under the Regulations, RDC may want the SA to consider assessing indicative higher and lower figures in future iterations. If felt necessary, this could also be expanded to assess reasonable spatial strategy options / permutations under different scenarios regarding levels of growth (i.e. at which level of growth would certain spatial strategy options be considered reasonable). Further, it may also be considered necessary to assess the figure included for the District in the recent DCLG consultation which set a standardised methodology for calculating housing needs. This is in consideration of the Plan being at an early stage of preparation and uncertainty as to what might be the District's OAN later on in the plan-making process.

ECC notes the reference throughout the SA and the Issues and Options Report, to 'a combination of options' and considers that whilst this may be a logical option in most cases, care needs to be taken as to what form a 'combined' policy would contain and aspire to.

ECC recommends that the "Climate Change" section should include a reference on whether the proposal will support the findings/priorities of the South Essex Surface Water Management Plan (2012 and emerging 2018 revision).

For instructions on how to use the system and make comments, please see our help guide.