MM14

Showing comments and forms 61 to 90 of 421

Object

HAAP: Schedule of modifications

Representation ID: 33016

Received: 08/01/2014

Respondent: Miss S Mead

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33019

Received: 08/01/2014

Respondent: Angela & Terence Elks

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33022

Received: 08/01/2014

Respondent: Mr Edward Barrett

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33025

Received: 08/01/2014

Respondent: Mrs Kaye Barrett

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33029

Received: 08/01/2014

Respondent: Louise Spiby

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33032

Received: 08/01/2014

Respondent: Maria Matsi

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

People do online shopping for heavy/large shopping, so no need for a bigger supermarket. It will be a waste, completely unnecessary.

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33035

Received: 08/01/2014

Respondent: mr&mrs geoffrey.doreen luderman

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33038

Received: 08/01/2014

Respondent: Mr Graham Meldrum

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33041

Received: 08/01/2014

Respondent: Mr and Mrs Gregory

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33044

Received: 08/01/2014

Respondent: Mr P J King

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33047

Received: 09/01/2014

Respondent: MR DAVID PUMFRETT

Representation Summary:

Detrimental effect on existing local businesses. Adequate shopping facilities exist already. Irreparable damage to the existing character of Hockley as a small village, turning it into a busy town centre.

Full text:

Detrimental effect on existing local businesses. Adequate shopping facilities exist already. Irreparable damage to the existing character of Hockley as a small village, turning it into a busy town centre.

Object

HAAP: Schedule of modifications

Representation ID: 33050

Received: 09/01/2014

Respondent: Stephanie Poole

Representation Summary:

It is not financially worth it as we already have 2 supermarkets

Full text:

It is not financially worth it as we already have 2 supermarkets

Object

HAAP: Schedule of modifications

Representation ID: 33055

Received: 10/01/2014

Respondent: MR ARTHUR COVER

Representation Summary:

Another supermarket is not required in Hockley.
Hockley is a village. Dont ruin it.

Full text:

Another supermarket is not required in Hockley.
Hockley is a village. Dont ruin it.

Comment

HAAP: Schedule of modifications

Representation ID: 33070

Received: 11/01/2014

Respondent: Ms Joanne Pass

Representation Summary:

I support an updated viability and financial analysis of this proposal.

Full text:

I support an updated viability and financial analysis of this proposal.

Object

HAAP: Schedule of modifications

Representation ID: 33073

Received: 12/01/2014

Respondent: Hockley Residents Association

Representation Summary:

The Financial Assessment in the HAAP incorrectly omits land assembly costs and means the proposals are not viable.
There is no demand for offices in Hockley further weakening the financial assessment.
The proposals are not financially viable and an updated assessment is required.

Full text:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable.

The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice. The changes may well impact the financials and an updated viability analysis is required.

Evidence:
The HAAP states: "This analysis adopts realistic and robust assumptions, including construction costs based on standard building indices and the project team's knowledge of comparable schemes, and takes into account the potential cost of land assembly. It also relates to a scheme that would help to meet the Council's aspirations for the AAP area. Broadly speaking, the viability analysis demonstrates that the proposed redevelopment of the Eldon Way Opportunity Site is currently financially viable".
So the HAAP recognises the financial analysis is marginal but states that land assembly costs are included. However, the actual, source Viability Assessment paper states land assembly costs are NOT included (as indeed they are not!). No evidence the plan is financially viable.
The revised HAAP designates Hockley as a prime location for the provision of new office space in the District. There is no evidence to support this proposal - recent demand for offices has been poor and in August 2013 the council approved a planning application to convert existing offices in a commercial property (Warren House), located in the village centre, into flats. Further, the letter dated Sept 2012 from GL Hearn (on the Evidence Base) confirms there is little demand: "Office development in Hockley would be seen as a secondary investment and as such it would be very difficult to secure private sector funding for any speculative office development in the short term and it is unlikely to be viable in any case. As a result of this weak demand profile, office provision in Hockley is limited at present. In summary, given the current economic climate and secondary nature of the Hockley office market it is unlikely that development would prove viable without significant cross subsidy from higher value uses or public sector support".
The existing industrial premises in Eldon Way currently provide a significant source of business to the adjacent shopping area. If demand for offices is low (as per the GL Hearn report), this trade will not be replaced and there will be a loss of business.

Object

HAAP: Schedule of modifications

Representation ID: 33114

Received: 10/01/2014

Respondent: Mr Alan Austin

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33118

Received: 13/01/2014

Respondent: Mrs Valerie Siegert

Number of people: 2

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33121

Received: 08/01/2014

Respondent: Mr Bennett

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33124

Received: 08/01/2014

Respondent: Mr and Mrs Andrews

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33127

Received: 08/01/2014

Respondent: Mr David Clarke

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33130

Received: 08/01/2014

Respondent: Mr and Mrs Lawrence

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33133

Received: 08/01/2014

Respondent: Mr and Mrs Thorn

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33136

Received: 08/01/2014

Respondent: Mr and Mrs K Adams

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33139

Received: 08/01/2014

Respondent: Mr B R Walker

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33142

Received: 08/01/2014

Respondent: Mr Edward Barrett

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33145

Received: 08/01/2014

Respondent: Mr and Mrs Searle

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33151

Received: 08/01/2014

Respondent: Mr and Mrs V P McCord

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33160

Received: 14/01/2014

Respondent: Mr Stuart Barham

Representation Summary:

The inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is no evidence that the revised overall proposals are financially viable. the original viability analysis as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own experts advice ( see Evidence Base Letter from GL Hearn). The changes may well impact the financials and an update viability analysis is required.

Full text:

The inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is no evidence that the revised overall proposals are financially viable. the original viability analysis as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own experts advice ( see Evidence Base Letter from GL Hearn). The changes may well impact the financials and an update viability analysis is required.

Object

HAAP: Schedule of modifications

Representation ID: 33165

Received: 13/01/2014

Respondent: The Co-operative Group

Agent: Barton Willmore LLP

Representation Summary:

MM14 - Policy 6

4. The Co-op maintains its objection to the revised Policy 6. In particular, the revised Policy 6 states that new A1 development within the Eldon Way Opportunity Site would be permitted where it would, amongst other things:

"b) Not exceed a maximum overall additional retail capacity for the centre of 3,000 sq m (gross)."

5. Whilst the detailed wording of criterion b) is not particularly clear, it has already been established that there is no capacity for convenience goods floorspace of 3,000 sq m gross in Hockley (either in or outside of the Centre). The only real difference to the revised criterion b) is that it no longer refers specifically to support for a foodstore. However, whilst the reference to a foodstore is removed, the use of the term 'retail' would clearly encompass both food (i.e. convenience) and non-food (i.e. comparison) retail. As such, the Policy would still support a foodstore of up to 3,000 sq m gross.

6. On the basis that there is no justification for a foodstore of up to 3,000 sq m gross, the Co-op maintains its position that the AAP is unsound.

7. In order for the AAP to be found sound, it is recommended that criterion b) is either deleted in its entirety or explicitly only permits comparison goods floorspace of up to 3,000 sq m gross, thus excluding any support for a foodstore.

8. The Co-op generally supports the inclusion of the additional requirements for a planning application after criterion d), however it should make it clear that all of the previous criteria need to be complied with and should be explicit that any planning application for retail development on the site will need to demonstrate compliance with the NPPF sequential and impact tests (paragraphs 24, 26 and 27 of the NPPF).

Recommended Changes To The Hockley Area Action Plan - Main Modifications Consultation

16. For the reasons set out above, the Co-op maintains its objection to the AAP, as proposed to be
modified. The following changes are proposed in order to make the Plan 'sound':

* MM14 - amend Policy 6 to either delete criterion b) or amend it so that it clearly does not support a
foodstore / convenience goods floorspace.
* MM14 - amend the final paragraph of Policy 6 after criterion d) in order to be clear that all previous
criteria need to be complied with and that any planning application is required to demonstrate
compliance with the NPPF sequential and retail impact tests.

Full text:

1. We act on behalf of the Co-operative Group ("the Co-op") and have been instructed to submit
representations and objections to the Main Modifications consultation on the Hockley Area Action Plan
("the AAP"). This follows the submission of previous representations in January 2013, a Hearing
Statement dated August 2013 and appearance at the Hearing Sessions held in September 2014. This
representation should be read in the context of our previous comments.
2. The Co-op's previous comments focused primarily on the allocation of a circa 3,000 sq m gross foodstore on the Eldon Way Site, under Policy 6 of the emerging AAP. During the Hearing Sessions and in its Hearing Statement, no evidence was provided by the Council to demonstrate that the proposed allocation of a foodstore of up to 3,000 sq m gross was justified against the evidence base, or was consistent with the NPPF. It could not therefore be considered sound. This view was supported by the Inspector in his letter to Rochford District Council dated 17th October 2013 which found that the proposed Policy 6 was unsound as there was no justification for a foodstore of 3,000 sq m gross.

3. Against this background, we set out below our comments to the Main Modifications to the AAP, and the AAP's performance against the soundness tests contained within the National Planning Policy Framework (NPPF) at paragraph 182.

Object

HAAP: Schedule of modifications

Representation ID: 33176

Received: 13/01/2014

Respondent: Mrs Mary Gajewska

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.