MM14
Object
HAAP: Schedule of modifications
Representation ID: 34179
Received: 17/01/2014
Respondent: Mrs J Nuttall
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34182
Received: 17/01/2014
Respondent: Mr and Mrs Marsh
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34185
Received: 17/01/2014
Respondent: Ms S E Greaves
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34188
Received: 17/01/2014
Respondent: Lee Smith
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34191
Received: 17/01/2014
Respondent: Mr and Mrs P Collins
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34194
Received: 17/01/2014
Respondent: Mr and Mrs Gravestock
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34197
Received: 17/01/2014
Respondent: Sharon Uden
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34200
Received: 17/01/2014
Respondent: Mr Darrell Uden
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34203
Received: 17/01/2014
Respondent: D J and M H Stringer
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34206
Received: 17/01/2014
Respondent: Mr and Mrs Wilhelmy
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34209
Received: 17/01/2014
Respondent: Mrs Sandra Blackwell
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34212
Received: 17/01/2014
Respondent: Mr Ralph Chapman
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34215
Received: 17/01/2014
Respondent: Mrs Gill Young
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34218
Received: 17/01/2014
Respondent: Mr K R Rose
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34221
Received: 17/01/2014
Respondent: Mrs M Huntley
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34224
Received: 17/01/2014
Respondent: MRS JULIE WIDDOWSON
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34227
Received: 17/01/2014
Respondent: Mr B Tracey
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34230
Received: 17/01/2014
Respondent: Mrs Jenny Andrews
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34233
Received: 17/01/2014
Respondent: Mrs Valerie Lowe
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34236
Received: 17/01/2014
Respondent: Tracey Lee
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34239
Received: 17/01/2014
Respondent: Mr Ronnie Billington
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34242
Received: 17/01/2014
Respondent: Mr Dean Stevens
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34245
Received: 17/01/2014
Respondent: Mrs V Colley
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34248
Received: 17/01/2014
Respondent: Mrs Dart
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34251
Received: 17/01/2014
Respondent: Mr George Lowe
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34254
Received: 17/01/2014
Respondent: Mr D Lever
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34257
Received: 17/01/2014
Respondent: Mr & Mrs B Smith
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34260
Received: 17/01/2014
Respondent: Mr Hemmings
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34263
Received: 17/01/2014
Respondent: Mrs Sandra Cornell
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.
Object
HAAP: Schedule of modifications
Representation ID: 34266
Received: 17/01/2014
Respondent: Mr Keith Watson
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.
MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.
MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.