MM14

Showing comments and forms 391 to 420 of 421

Object

HAAP: Schedule of modifications

Representation ID: 34179

Received: 17/01/2014

Respondent: Mrs J Nuttall

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34182

Received: 17/01/2014

Respondent: Mr and Mrs Marsh

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34185

Received: 17/01/2014

Respondent: Ms S E Greaves

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34188

Received: 17/01/2014

Respondent: Lee Smith

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34191

Received: 17/01/2014

Respondent: Mr and Mrs P Collins

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34194

Received: 17/01/2014

Respondent: Mr and Mrs Gravestock

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34197

Received: 17/01/2014

Respondent: Sharon Uden

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34200

Received: 17/01/2014

Respondent: Mr Darrell Uden

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34203

Received: 17/01/2014

Respondent: D J and M H Stringer

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34206

Received: 17/01/2014

Respondent: Mr and Mrs Wilhelmy

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34209

Received: 17/01/2014

Respondent: Mrs Sandra Blackwell

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34212

Received: 17/01/2014

Respondent: Mr Ralph Chapman

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34215

Received: 17/01/2014

Respondent: Mrs Gill Young

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34218

Received: 17/01/2014

Respondent: Mr K R Rose

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34221

Received: 17/01/2014

Respondent: Mrs M Huntley

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34224

Received: 17/01/2014

Respondent: MRS JULIE WIDDOWSON

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34227

Received: 17/01/2014

Respondent: Mr B Tracey

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34230

Received: 17/01/2014

Respondent: Mrs Jenny Andrews

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34233

Received: 17/01/2014

Respondent: Mrs Valerie Lowe

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34236

Received: 17/01/2014

Respondent: Tracey Lee

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34239

Received: 17/01/2014

Respondent: Mr Ronnie Billington

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34242

Received: 17/01/2014

Respondent: Mr Dean Stevens

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34245

Received: 17/01/2014

Respondent: Mrs V Colley

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34248

Received: 17/01/2014

Respondent: Mrs Dart

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34251

Received: 17/01/2014

Respondent: Mr George Lowe

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34254

Received: 17/01/2014

Respondent: Mr D Lever

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34257

Received: 17/01/2014

Respondent: Mr & Mrs B Smith

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34260

Received: 17/01/2014

Respondent: Mr Hemmings

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34263

Received: 17/01/2014

Respondent: Mrs Sandra Cornell

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34266

Received: 17/01/2014

Respondent: Mr Keith Watson

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.