MM14

Showing comments and forms 361 to 390 of 421

Object

HAAP: Schedule of modifications

Representation ID: 34089

Received: 17/01/2014

Respondent: Mr and Mrs Polley

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34092

Received: 17/01/2014

Respondent: Mr & Mrs Whiten

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34095

Received: 17/01/2014

Respondent: S A Swinscoe

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34098

Received: 17/01/2014

Respondent: Richard Jarrard

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34101

Received: 17/01/2014

Respondent: Derek Nicholls

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34104

Received: 17/01/2014

Respondent: Mrs Eileen Nicholls

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34107

Received: 17/01/2014

Respondent: Mr & Mrs I Cooper

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34110

Received: 17/01/2014

Respondent: Mr and Mrs Bransbury

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34113

Received: 17/01/2014

Respondent: Mr P Ensum

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34116

Received: 17/01/2014

Respondent: Mrs F G Connell

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34119

Received: 17/01/2014

Respondent: Mr and Mrs R Mason

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34122

Received: 17/01/2014

Respondent: Mr J Uden

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34125

Received: 17/01/2014

Respondent: Chris Blanchard

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34128

Received: 17/01/2014

Respondent: Miss S Carter

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34131

Received: 17/01/2014

Respondent: Mr and Mrs Lott

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34134

Received: 17/01/2014

Respondent: Miss Julie Lott

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34137

Received: 17/01/2014

Respondent: Mr E Ramsey

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34140

Received: 17/01/2014

Respondent: Gillian Donohue

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34143

Received: 17/01/2014

Respondent: Lynda Nice

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34146

Received: 17/01/2014

Respondent: Mr and Mrs Frost

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34149

Received: 17/01/2014

Respondent: Mr and Mrs Atheis

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34152

Received: 17/01/2014

Respondent: Mr & Mrs Payne

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34155

Received: 17/01/2014

Respondent: Mrs Laura-Jane Craddock

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34158

Received: 17/01/2014

Respondent: Hockley Hawkwell Women's Institute

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34161

Received: 17/01/2014

Respondent: Mr and Mrs Isherwood

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34164

Received: 17/01/2014

Respondent: Mr and Mrs Woracker

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34167

Received: 17/01/2014

Respondent: Mrs S Adkins

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34170

Received: 17/01/2014

Respondent: Mrs Meredith Coombes

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34173

Received: 17/01/2014

Respondent: Mr Barry Craddock

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 34176

Received: 17/01/2014

Respondent: Miss S Joyce

Representation Summary:

The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.