MM7

Showing comments and forms 61 to 90 of 423

Object

HAAP: Schedule of modifications

Representation ID: 33009

Received: 08/01/2014

Respondent: Mr and Mrs Brown

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33012

Received: 08/01/2014

Respondent: Mr and Mrs A F Woodward

Number of people: 2

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33015

Received: 08/01/2014

Respondent: Miss S Mead

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33018

Received: 08/01/2014

Respondent: Angela & Terence Elks

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33021

Received: 08/01/2014

Respondent: Mr Edward Barrett

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33024

Received: 08/01/2014

Respondent: Mrs Kaye Barrett

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Comment

HAAP: Schedule of modifications

Representation ID: 33027

Received: 09/01/2014

Respondent: Mrs Jeannette Bennett

Representation Summary:

I am writing to object to major development in Hockley. Further housing and retail units in Eldon Way will only add to the already awful traffic problems in the village. Traffic jams created by allowing lorries to unload every morning outside Sainsburys cause serious problems to those of us who have to commute by car to work. I understand the need for housing but in the middle of a quiet village is not the place, and this is not a case of NIMBY but I worry about the lack of decent transport links, lack of school places, doctors, dentists etc

Full text:

I am writing to object to major development in Hockley. Further housing and retail units in Eldon Way will only add to the already awful traffic problems in the village. Traffic jams created by allowing lorries to unload every morning outside Sainsburys cause serious problems to those of us who have to commute by car to work. I understand the need for housing but in the middle of a quiet village is not the place, and this is not a case of NIMBY but I worry about the lack of decent transport links, lack of school places, doctors, dentists etc

Object

HAAP: Schedule of modifications

Representation ID: 33028

Received: 08/01/2014

Respondent: Louise Spiby

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33031

Received: 08/01/2014

Respondent: Maria Matsi

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

People do online shopping for heavy/large shopping, so no need for a bigger supermarket. It will be a waste, completely unnecessary.

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33034

Received: 08/01/2014

Respondent: mr&mrs geoffrey.doreen luderman

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33037

Received: 08/01/2014

Respondent: Mr Graham Meldrum

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33040

Received: 08/01/2014

Respondent: Mr and Mrs Gregory

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33043

Received: 08/01/2014

Respondent: Mr P J King

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33046

Received: 09/01/2014

Respondent: MR DAVID PUMFRETT

Representation Summary:

Increased volume of traffic will cause parking issues for local residents and congestion in the small town centre.

Full text:

Increased volume of traffic will cause parking issues for local residents and congestion in the small town centre.

Object

HAAP: Schedule of modifications

Representation ID: 33049

Received: 09/01/2014

Respondent: Stephanie Poole

Representation Summary:

Hockey's road system is not sufficient to cope with extra traffic or larger lorries

Full text:

Hockey's road system is not sufficient to cope with extra traffic or larger lorries

Object

HAAP: Schedule of modifications

Representation ID: 33054

Received: 10/01/2014

Respondent: MR ARTHUR COVER

Representation Summary:

The traffic problems in Hockley are not going to be helped in any way by building a supermarket that is not required.
Sainsburys new shop in Hockley (Not needed by residents) is already causing congestion to Spa Road with gigantic delivery lorries.

Full text:

The traffic problems in Hockley are not going to be helped in any way by building a supermarket that is not required.
Sainsburys new shop in Hockley (Not needed by residents) is already causing congestion to Spa Road with gigantic delivery lorries.

Comment

HAAP: Schedule of modifications

Representation ID: 33069

Received: 11/01/2014

Respondent: Ms Joanne Pass

Representation Summary:

I strongly support a full transport assessment being carried out and I hope that due consideration will be given to the avoidance of making Hockley centre a bottle-neck and being unable to provide a free-flow of traffic.

Full text:

I strongly support a full transport assessment being carried out and I hope that due consideration will be given to the avoidance of making Hockley centre a bottle-neck and being unable to provide a free-flow of traffic.

Object

HAAP: Schedule of modifications

Representation ID: 33074

Received: 12/01/2014

Respondent: Hockley Residents Association

Representation Summary:

The council has suppressed the work undertaken by consultants on a Transport Assessment. Why?
The change away from an anchor supermarket means it is less likely there will be a "strategic" development so a Transport Assessment is essential.

Full text:

The revised wording dilutes the requirement for a Transport Assessment to "strategic planning applications". With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such "strategic planning applications" will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Evidence:
A Freedom of Information (FoI) response from RDC acknowledged Transport Assessments had been undertaken in Rochford & Rayleigh but refused to release them. What happened to them and why was one not undertaken for Hockley?
Another FoI response revealed work has started on assessing highways issues. The outcome of that work has never been made public - a RDC FoI response denied receiving any output from this work - and presumably kept by the external consultancy. What happened to it and why has it been suppressed? Residents should be able to view the work that RDC commissioned - what are they hiding?
The council has consistently mislead residents by repeatedly stating at every stage, highways issues would be included in the HAAP but, in fact, excluded them.
There is no evidence to support proposals to insert slip lane and widen pavement for 3 extra slip-lanes at the Spa roundabout are viable and have not been properly researched, despite previous promises. FoI responses show RDC's own experts have expressed reservations
Other problem areas such as the railway bridge and Eldon Way junction are not even mentioned.
Proposal to raise access to Woodlands Road likely to cause delays on main road and endanger pedestrians.
The B1013 was assessed many years ago (Sept 2008) by ECC Highways as nearing capacity but no updates despite much increased traffic volumes. Why haven't capacity updates been undertaken?
No Transport Assessment has been undertaken for Core Strategy (as well as the HAAP). A Traffic Assessment is required to ascertain the impact on Hockley of the 3,500 additional homes to be built across the District as part of the Core Strategy.
The council committed to produce a Transport SPD but has not done so.

Object

HAAP: Schedule of modifications

Representation ID: 33113

Received: 10/01/2014

Respondent: Mr Alan Austin

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Comment

HAAP: Schedule of modifications

Representation ID: 33116

Received: 13/01/2014

Respondent: Mr James Hunter

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to ''strategic planning applications''. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee that any such ''strategic planning applications'' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misles us , the residents and undertaken u-turn on repeated commitments to undertake a Transport Assessment as part of thye HAAP.Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

The revised wording dilutes the requirement for a Transport Assessment to ''strategic planning applications''. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee that any such ''strategic planning applications'' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misles us , the residents and undertaken u-turn on repeated commitments to undertake a Transport Assessment as part of thye HAAP.Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Object

HAAP: Schedule of modifications

Representation ID: 33117

Received: 13/01/2014

Respondent: Mrs Valerie Siegert

Number of people: 2

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33120

Received: 08/01/2014

Respondent: Mr Bennett

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33123

Received: 08/01/2014

Respondent: Mr and Mrs Andrews

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33126

Received: 08/01/2014

Respondent: Mr David Clarke

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33129

Received: 08/01/2014

Respondent: Mr and Mrs Lawrence

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33132

Received: 08/01/2014

Respondent: Mr and Mrs Thorn

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33135

Received: 08/01/2014

Respondent: Mr and Mrs K Adams

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33138

Received: 08/01/2014

Respondent: Mr B R Walker

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33141

Received: 08/01/2014

Respondent: Mr Edward Barrett

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.

Object

HAAP: Schedule of modifications

Representation ID: 33144

Received: 08/01/2014

Respondent: Mr and Mrs Searle

Representation Summary:

The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

Full text:

MM7 -
The revised wording dilutes the requirement for a Transport Assessment to 'strategic planning applications'. With the emphasis on smaller 'boutique' businesses, there is no longer any guarantee any such 'strategic planning applications' will be made. There are therefore no effective proposals or evidence to deal with highways issues (Chapter 3, Policy 3) and the council has consistently misled residents and undertaken a U-turn on repeated commitments to undertake a Transport Assessment as part of the HAAP. Smaller developments may also mitigate against meaningful improvements. A clear commitment to a full transport assessment is required.

MM14 -
The Inspector's changes correctly and appropriately reflect the findings of the Retail & Leisure Study 2008 but the changes will impact on the project finances and there is absolutely no evidence that the revised overall proposals are financially viable. The original viability analysis, as presented in the submission copy of the HAAP contained a major error (omitting land assembly costs) and the plans for more offices are contrary to their own expert's advice (see Evidence Base letter from GL Hearn). The changes may well impact the financials and an updated viability analysis is required.

MM16 -
The proposals will materially change the character of Hockley by demolishing around 2/3 of the village centre. This change of character has not been consulted on (but responses to previous consultations show it is heavily opposed.) The scale of change is relatively huge but little benefit and none of the key issues resolved - a poor plan which will damage Hockley.