Option 3a

Showing comments and forms 31 to 60 of 154

Object

Hockley Area Action Plan Options Report

Representation ID: 26864

Received: 17/01/2011

Respondent: Mr and Mrs Poole

Representation Summary:

Inappropriate changes and over development.

Full text:

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions

Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

The Options proposed overleaf seem a sensible and practical proposal that enhances many aspects of the village/town without removing its identity. Lets just have it tidied up and presentable and done.

Comment

Hockley Area Action Plan Options Report

Representation ID: 26872

Received: 04/02/2011

Respondent: Maria/Edmund Tugwell

Representation Summary:

Option 3a is an improvement on Option 3, as long as the existing leisure space is retained with the existing facilities. A skating rink is also very welcome.

Full text:

Option 3a is an improvement on Option 3, as long as the existing leisure space is retained with the existing facilities. A skating rink is also very welcome.

Object

Hockley Area Action Plan Options Report

Representation ID: 26895

Received: 17/01/2011

Respondent: Graham Howorth

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26902

Received: 04/01/2011

Respondent: Mr K Goodchild

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26909

Received: 07/01/2011

Respondent: Mrs Margaret Christian

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26916

Received: 10/01/2011

Respondent: Mrs L.D Rumsey

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26923

Received: 10/01/2011

Respondent: Miss Melissa Hart

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26930

Received: 10/01/2011

Respondent: Mr J Morrison

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26937

Received: 13/01/2011

Respondent: Mrs Kay ILOTT

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26944

Received: 13/01/2011

Respondent: Ms D Hartwell

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26951

Received: 13/01/2011

Respondent: Ms H Rozga

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26958

Received: 14/01/2011

Respondent: Mr and Mrs Bowry

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26965

Received: 14/01/2011

Respondent: Mr and Mrs Cross

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26972

Received: 14/01/2011

Respondent: Mrs L Tate

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26979

Received: 17/01/2011

Respondent: Mrs T Jacques

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26986

Received: 17/01/2011

Respondent: Mrs Anne Ockelford

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 26993

Received: 14/01/2011

Respondent: Mr P R Hunt

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27000

Received: 14/01/2011

Respondent: Mrs Andrea Boyce

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27007

Received: 14/01/2011

Respondent: Mrs L Tate

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27014

Received: 14/01/2011

Respondent: Mrs L Maxim

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27021

Received: 17/01/2011

Respondent: Ms B Beckwith

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27028

Received: 17/01/2011

Respondent: Mrs M Woolcott

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27035

Received: 12/01/2011

Respondent: D S Buchanan

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27042

Received: 21/01/2011

Respondent: Ms M Robbins

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27049

Received: 21/01/2011

Respondent: Ms L T Oliver

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27056

Received: 21/01/2011

Respondent: Mr R J Syrett

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27063

Received: 24/01/2011

Respondent: Mr and Mrs Price

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27070

Received: 24/01/2011

Respondent: Mrs M Huntley

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27077

Received: 04/02/2011

Respondent: Mr Jamie Dowie

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road

Object

Hockley Area Action Plan Options Report

Representation ID: 27084

Received: 07/02/2011

Respondent: L Chester

Representation Summary:

Inappropriate changes and over development.

Full text:

HAAP Consultation January 2011

I wish to register the following objections regarding the above consultation:

Chapter 4. Overarching Frame work: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements.

Option 1: Object: Insufficient benefits.

Option 2a: Object: Inappropriate changes and missed opportunities.

Options 3: Object: Inappropriate changes and over development.

Options 3a: Object: Inappropriate changes and over development.

Chapter 8. Transport options: Object: Previous consultations have made clear that highways infrastructure improvements to the key junctions at: Spa roundabout; Eldon Way; Station Approach and Plumberow need to be determined as a precursor to any redevelopment. Insufficient attention has been paid to these key requirements and the sketch proposals provided have not been researched and may not be viable.

Option 2: Object: This option forms the basis of an appropriate plan but does not go far enough but support an enhanced version as follows (changes in italics):

Roads (key priority and subject to viability confirmation)

Improvements to Spa Roundabout e.g. Slip lanes or Table top crossing
Improvements to Eldon Way, Station Approach, and Plumberow junctions
Road widening of Spa Road from Co-Op supermarket to railway bridge


Parking:

Added/Consolidated parking square behind shops on west side of Spa Road reached via Eldon Way and (if possible) Bramerton Rd
Added on-street parallel parking in Spa Road and pick-up/drop-off points both sides of Hockley Station

Building changes

Redevelop shops on Southside of Main Road, opposite Potters, to remove 'pinch -point' on B1013
Change from retail to housing at Costcutters Parade of shops
Modernised retail units with 4 flats above Seemore Glass
Modernised retail units with 2 added retail units at Factory Shop/Car park area (to remain single storey)
Redevelop Co-Op Undertakers etc and extend to join existing shops either side, removing access roads creating additional Retail
Community centre with library/health centre/shops at current library location with 13 flats and 2 retail units
2 large format retail units in Eldon Way (delete from proposals)
Replacement of one industrial building with light industry/ offices/ parking square on Eldon Way
Retail unit near station in Spa Road replaced by house
Housing on north side of Station along Plumberow Ave, to include railway drop-off point
Retail option (possibly a market) to be considered for Sorting Office site
Options for undeveloped portion of Foundry Estate to be considered.

General

Enhanced station frontage & Pedestrian link to Eldon Way (but care re safety considerations)
Enhanced shop fronts, paving and streetscape Spa Road / Main Road / Southend Road
Improved safety, consolidated and new leisure space on Eldon Way
Flexible employment opportunities, enhanced frontages to leisure/other buildings on Eldon Way
New link through Catholic Church from Spa Road to Southend Road