Object
Core Strategy Submission Document
Representation ID: 16350
Received: 22/10/2009
Respondent: Aber Ltd
Agent: Colliers International
Legally compliant? Yes
Sound? No
Duty to co-operate? Not specified
In addition, to the general location and development been articulated within the Allocations Development Plan Document, in accordance with the requirement of PPS3 the specific sites should also be delineated on the Proposals Map.
This approach is consistent with the need to maintain flexibility in order to ensure certainty to the delivery of the 15 year supply, particularly if any of the locations identified in the period post 2021 need to be brought forward in order to maintain the 5 year supply. This may requier the release of land from the Green Belt ahead of the development of all the sites in Policy H2.
In addition, to the general location and development been articulated within the Allocations Development Plan Document, in accordance with the requirement of PPS3 the specific sites should also be delineated on the Proposals Map.
This approach is consistent with the need to maintain flexibility in order to ensure certainty to the delivery of the 15 year supply, particularly if any of the locations identified in the period post 2021 need to be brought forward in order to maintain the 5 year supply. This may requier the release of land from the Green Belt ahead of the development of all the sites in Policy H2.
Amend first paragraph as follows:
Post-2021, the residential envelope of existing settlements will be extended in the following areas (as indicated on the Key Diagram) to deliver the following number of units post-2021. Prior to this time, Green Belt land within such areas will be safeguarded with the exception of land that is required to maintain a continuous 5 year supply of land in accordance with Policy H2.
Amend second paragraph as follows:
The detailed location and quantum of development will be articulated within the Allocations Development Plan Document, and delineated on the Proposals Map.